Anonymized example, illustrative — built from a typical case, not a real client file. Every real report follows this structure: findings, citations, fair-price range, and a counterproposal ready to send.

Change Order Review — Example

CO #3 — Retail Buildout, Suite 210

Summary of findings

Of $71,700 requested, $19,300 (27%) is either already covered by base scope or exceeds your contract's markup cap. Fair-price range for the change order as submitted: $48,900–$52,400.

Markup analysis

Contract cap (§7.1)10%
Markup applied on CO #318%
18% > 10% cap — overage on $52,400 base = $4,192

Scope overlap

"Framing & rough-in" is billed at $52,400, but is already listed under base contract §4.2.

Already in scope — §4.2

Unsubstantiated items

"Miscellaneous project coordination — $12,400" and "Overtime as required — $6,900" carry no unit rate, hours, or basis.

No unit / basis — flag

Counterproposal (ready to send)

"Per §4.2, framing & rough-in is already within base scope and is removed from CO #3. Per §7.1, markup is capped at 10%; the applied 18% is adjusted down by $4,192. Miscellaneous coordination and overtime require a unit basis or hourly log before approval. Revised CO #3 total: $52,400 → $48,900–$52,400 pending substantiation."